Although migration projects differ in complexity, there is a common theme in how to approach the migration journey.
Migration journeys
The complexity of Camunda-7-based solutions varies significantly. Solutions range from small implementations with clean delegates to large solutions with hundreds of processes using internal API hacks.
This guide covers two typical journeys - a simplified migration journey and an advanced migration journey.
Simplified migration journey
Suitable for solutions that are easy to migrate. If your solution fits into this category, migrating to Camunda 8 is straightforward.
Advanced migration journey
For more complex solutions that require tackling additional complexities.
Maybe the truth will be somewhere in the middle for you. As a rule of thumb, Camunda advises keeping things as simple as possible (but of course not simpler).
Let's explore the various steps in more detail. You might skip some steps if a simplified journey is sufficient.
1Orient yourself
First, understand what needs to be done to migrate and what effort to expect. This allows you to plan and budget a migration project properly. Important steps include:
- Understand conceptual differences between Camunda 7 and Camunda 8.
- Analyze your solution to understand required changes based on your models.
- Explore code conversion patterns.
- Estimate migration effort and budget the project.
- Define your target Camunda version and derive a migration timeline.
- Leverage advisory services from Camunda consulting or certified partners.
After orientation, you can plan your migration project and start two independent work streams:
But first, let's understand orientation in more detail.
Analyze your solution
Camunda is developing the Migration Analyzer, a tool to understand migration tasks. This tool is based on the existing diagram converter, which can be used via CLI to produce a CSV file with tasks in your model. Our consultants then import this data into a Google Spreadsheet template to analyze what tasks need to be done to migrate. The following screenshot shows a sample report.
To add some real-world flavor: In a customer scenario, our consultants ran 400 BPMN files through the tool, resulting in roughly 12,000 lines of findings. Analyzing those lines using the spreadsheet reduced that number to roughly 30 different types of tasks, making the migration project manageable.
This analysis will help you understand what needs to be done to migrate.
Estimate migration effort and budget project
This analysis is the basis for estimating migration efforts. Our consultants use rule-of-thumb numbers on how much effort typical tasks require. For example, converting a Camunda 7 Java Delegate to a Camunda 8 Job Worker might take one hour if it just involves refactoring the JavaDelegate. It might take more effort if internal Camunda API is used in the delegate. Looking at code conversion patterns allows you to come up with your own estimate, which you can multiply by the number of tasks from the analyzer.
In past migration projects, this gave us a good ballpark estimation to plan and budget the project.
When to migrate?
Any new projects should already be started using Camunda 8.
For Camunda 7 solutions, understand the support timeline for the Camunda 7 product:
- Camunda 7 CE (Community Edition) will EOL (end of life) in October 2025 with a final release (v7.24) on Oct 14, 2025.
- There will be no more Camunda 7 CE releases after that date, and the GitHub repo will be archived. The code will still be available, but issues and pull requests will be closed, and the README will reflect the EOL status.
- Camunda 7 EE (Enterprise Edition) customers will continue to get patch releases (security patches & bug fixes) on a rolling basis till at least 2030.
- Camunda 7 CE users could switch to Camunda 7 EE to benefit from this long-term support to have enough time for migration.
While there is some urgency to start migration efforts, you are not yet under hard pressure.
Migrating to Camunda 8 gives you additional advantages, which might raise priority for your solution if:
- You want to leverage a SaaS offering (for example, to reduce the effort for hardware or infrastructure setup and maintenance).
- You need performance at scale and/or improved resilience.
- You need certain features that can only be found in Camunda 8 (for example, BPMN message buffering, improved multi-instance handling, the new Connectors framework, RPA, IDP, or the improved collaboration features in Web Modeler).
When not to migrate?
You might wonder if there are cases where migration doesn't make sense? Camunda basically sees two scenarios here:
- Your solution is in legacy mode and will approach its own end of life before Camunda ends support.
- Your solution relies on an architecture that is not possible with Camunda 8. For example, software vendors that embedded Camunda 7 as a Java library into their own build, relying on shipping exactly one self-contained Java application. Refer to conceptual differences for technical details. Most often, you could still migrate those scenarios if you rearchitect the solution.
Define your target Camunda version for migration
Because of the improved core architecture of Camunda 8, features need to be re-added to Camunda 8 step-by-step. That means the current Camunda 8 version might not yet have sufficient feature parity for your scenario to migrate. Prominent examples are task listeners (which will be introduced with 8.8) or the business key (planned for 8.9).
If your solution requires those features, it might make sense to wait for the Camunda 8 version that will provide these features. You can check the public feature roadmap to understand timelines.
The Camunda version to target might differ per process solution. For example, Process A might not need additional features and can migrate right away, but Process B might use the business key planned for 8.9. That means you wait for rolling out migration for Process B till that version. As Camunda is currently running an architecture streamlining initiative to improve the core architecture, which will be released with Camunda 8.8. Unless you have time pressure or momentum to lose, Camunda generally recommends waiting for this to happen and targeting a Camunda version >= 8.8 for migration.
For example, targeting the 8.9 release doesn't mean you wait for it to happen before thinking about migration. Typically, you can already perform analysis (which you might need to do anyway to understand the right target version), which is also important to plan your project and apply for the required budget on time. Doing the migration tasks can also happen before the actual release, either independently or based on early alpha versions.
Leverage guidance, advisory, and tooling
This guide is the main resource walking you through migration.
As part of your migration journey, you might also want to consider engaging professional services to help you. The main starting points are:
- Migration evaluation workshop (Camunda)
- Scoping Workshop (Camunda)
- Professional advisory services (Camunda, Partners)
- Implementation services (Partners)
Furthermore, you can use the migration tooling and related resources.
2Set Up Camunda 8
To run any solution on Camunda 8, you must have a running Camunda 8 installation.
If you used an embedded engine with Camunda 7 in the past, this model is no longer possible (see conceptual differences between Camunda 7 and Camunda 8). This might be new to your organization to operate Camunda in addition to your solution itself. The most successful operating model is to have a central team in the organization caring about Camunda, offering it as a self-service platform to others. This is also described in our process automation Center of Excellence playbook.
We want to unmask some typical misconceptions with Camunda 8:
- Camunda 8 does not need to be consumed as SaaS! But you can use SaaS if you want.
- Camunda 8 does not mean there needs to be one huge cluster to rule them all! But you can run big workloads on one cluster.
- Camunda 8 does not need to be set up for horizontal scalability! But you can set this up if you want.
You can run small Camunda 8 installations, one per solution if you like. They can all be Self-Managed, meaning they run in your own datacenter. With the architecture streamlining and the RDBMS initiative, Camunda provides a very simple Java installation (single JAR) that removes installation complexity and is sufficient for many use cases (RDBMS is planned for release with Camunda 8.9).
There are multiple ways to set up Camunda 8:
-
Use Camunda's SaaS offering: You don't need to install or operate the platform yourself. This is the most convenient and generally recommended option. If you face legal challenges around information security, privacy, and compliance, check the Camunda Trust Center. Note that this option comes with limitations. For example, you can't migrate historical audit data from Camunda 7 to Camunda 8 SaaS, and multi-tenancy will be introduced in SaaS with Camunda 8.8.
-
Run the platform Self-Managed. You might want to look at the Camunda 8 Run distribution. RDBMS support is planned to be introduced with 8.9, removing the need for Elastic Search and allowing a relatively simple setup that Camunda 7 users often like. Still, you can go for more scalable options (see also the architecture streamlining blog post). Refer to the installation guide for details.
While setting up Camunda 8 is not part of the core migration journey, it is a prerequisite and should be tackled early in the migration journey to avoid blockers.
3Making Core Decisions
There are a small number of core decisions that will influence your overall migration journey. Although you might make them later in your journey once you have a better understanding of the consequences, Camunda presents them here so that you have them top of mind for the remainder of this guide.
Drain-out vs big bang
There are two possible migration scenarios: Drain out and big bang.
Both are valid approaches. Let's briefly look at the differences.
-
Drain out: Keep running the C7-based solution, but run the C8-based (migrated) solution in parallel. New process instances are started in the new one. After some time, no processes are active in C7 any more, and the C7-based solution can be decommissioned.
-
Big bang: The solution is migrated from C7 to C8, including data migration scripts. At one moment in time, the C7-based solution is stopped, the data is migrated, and the new C8-based solution is started. This C7 solution can be decommissioned right after. Note that a big bang relates to one process solution only. So if you run multiple processes, you typically migrate them one by one in multiple big bangs, not in one super big bang. For any of those processes, when you migrate, you flip the switch and are on C8 for those processes.
Let's look at the pros and cons of each approach.
Drain out
Pros:
- No downtime.
- No data migration required.
- Easy fallback to old solution in case of problems.
Cons:
- Requires code switch (for example, forwarding messages to either C7 or C8 depending on where the corresponding process was started).
- Duplicate tooling (for example, one Tasklist for C7 and one for C8 processes; same for operators with Cockpit and Optimize).
- Need to operate two solutions at the same time.
Big bang
Pros:
- Only one solution is running.
- No code switches necessary.
- No need to support the legacy codebase.
Cons:
- Requires data migration, at least runtime instances, which has some limitations (see migration tooling).
- Complexity of the necessary data migration might drive effort.
- Might require downtime.
There are some scenarios where process instances are short-lived, and the big bang approach can simply drain out existing instances and then restart without the need for data migration, making migration simpler.
Recommendation
There is no general recommendation for which strategy to use.
You could consider the big bang approach less complex in many scenarios. However, there are some indicators to use drain out instead:
- Short-lived processes: If processes finish quickly, the drain out happens fast, and it might even be possible to delay new process starts until after the drain out has happened.
- Latency-sensitive processes: Some use cases can't stand the outage time required for data migration. Maybe you can delay data migration and do it after you have already switched to the C8-based solution. Otherwise, big bang might simply not be feasible or require a more sophisticated data migration strategy.
- Risk: If your use case carries a lot of risk, you might not feel comfortable with the big bang. Most often, this can be mitigated by properly testing your migration.
- No switching logic required: Maybe running the C8-based solution in parallel requires almost no effort on your end (as you don't have user tasks or message receive events), then it might be the simpler choice.
- Complexity of data migration: If data migration turns out to be complex in your solution, draining out might be the better choice.
Migrating your solution landscape step-by-step
If you run multiple process solutions, you best migrate them one by one.
You can also drive this idea one step further. If you have complex solutions with multiple BPMN models, call activities, and further dependencies, even migrating those solutions in one go might be overwhelming. In this case, you could apply a microservices mindset and adjust your call activities to be service calls to other components. This way, you could migrate that solution process by process. This is not a general recommendation, just illustrating possibilities to reduce the migration scope.
Adapt existing code vs refactoring
You need to adjust the code of your solution during migration. There are two general possibilities:
- Keep existing code written for Camunda 7 and add an adapter to run it with Camunda 8. The Camunda 7 Adapter is a starting point for doing this.
- Refactor your code to work with Camunda 8. The code conversion part of this guide will focus on this approach.
We generally recommend refactoring your code. Let's briefly dive into both options.
Adapt existing code
While this approach sounds easy at first glance, it typically works only with very cleanly implemented Java Delegates (which could also be simply refactored to Job Workers). Even if using an adapter, you still need to understand architectural implications (such as transactional boundaries) and might need to rewrite some code. It also does not adapt all assets (for example, the Camunda 7 service API or test cases are not adapted).
In general, the adapter approach is rarely used.
Refactor your code
Rewrite your code. This follows typical patterns and might even be automated to some extent using OpenRewrite recipes. See the code conversion guide for details.
This approach has the big advantage that the resulting solution will comply with best practices on how Camunda 8 solutions should be written. Furthermore, architectural differences can be better understood while refactoring the solution. Some projects are also happy to clean up a codebase that has grown over time, reducing technical debt as part of the migration effort.
The downside is the effort required to refactor. The best strategy is to not over-engineer the approach for small code bases, but to automate migration of big code bases as much as possible.
4Migrate solution(s)
The main tasks to migrate your solutions to run on Camunda 8 include:
- Prepare your Camunda 7 solution (optional)
- Convert models
- Convert expressions
- Refactor code
- Improve Camunda 8 Solution (optional)
Let's dive into the details of these tasks.
Prepare your Camunda 7 solution (optional)
It can make sense to do a first refactoring step in your Camunda 7 codebase to prepare for easier migration. The advantage of this approach is that you can make changes in a codebase and environment you understand well, while you can still run existing test cases without changes, derisking any changes you make.
Typical preparation steps include:
-
Extract complex code from your JavaDelegates into Camunda-independent classes (for example, Spring beans) that are then invoked from the original JavaDelegate. This way, you do a step towards Clean Delegates that will be easy to refactor.
-
Remove the usage of internal APIs or calls that depend on the transactionally integrated architecture of Camunda 7 (for example, querying the HistoryService within a JavaDelgate and expect it to know current changes already).
-
Increase test coverage of the solution to increase confidence that code conversions during migration do not break anything. This is especially important if your C7-based solutions lack good test coverage. To avoid migration effort on test cases, ideally abstract the test cases from the Camunda version used, either by using a small own abstraction layer, or by using a test framework such as Cucumber or Sentinel.
-
Structural changes in your BPMN model to make them runnable on Camunda 8. One trigger could be that you are using constructs that are not supported in Camunda 8 (for example, execution listeners on sequence flows). Or you want to get your models into a state that allows runtime data migration (see data migration), for example by adding artificial wait states before multi-instance tasks (as multiple instance is not supported for runtime data migration).
-
Replace JUEL expressions with FEEL. JUEL is not supported in Camunda 8 (see conceptual differences). We plan to release a FEEL plugin for the Camunda 7 platform, allowing you to already rewrite your expressions within your Camunda 7 environment. This change goes beyond simply converting JUEL to FEEL, but also removing any calls to Spring beans that are not possible in FEEL. So you might, for example, add execution listeners invoking the code you need, writing a process variable that then can be evaluated in FEEL.
This step is optional and can also be skipped, either because the codebase is already in a clean state or you are feeling confident about directly converting your codebase to Camunda 8.
Convert models
Your BPMN and DMN models need to be adjusted.
The Diagram Converter takes care of most changes. Depending on how you refactor your code and what elements of Camunda 7 you have used, you can extend or customize the diagram converter to suit your needs.
You can dive into the technical details of model differences if you are interested in more detail.
Convert expressions
Your models might contain JUEL expressions, which are not supported in Camunda 8.
Simple expressions are directly converted by this code in the Diagram Converter.
You can use the FEEL copilot to rewrite more complex expressions for you.
Check the code conversion patterns section for more complicated scenarios.
Refactor code
You need to refactor your code to use Camunda 8 APIs only.
Most prominently you need to convert any API calls to Camunda (for example, RuntimeService) and the glue code attached to process models (for example, JavaDelegates). The code conversion patterns goes into more details how to approach this. Some of those changes might be automated using OpenRewrite recipes.
Depending on your architecture you might also have to re-architect core parts of your solution. This is especially true if you rely on transaction integration, threading, internal API (such as calling the HistoryService from within a JavaDelegate), or features that are deprecated and thus are not planned for Camunda 8 (such as CMMN). See conceptual differences between Camunda 7 and Camunda 8 for more details on this.
As part of this effort you also have to adjust your test cases. If you used camunda-bpm-assert, a natural choice is to migrate to Camunda Process Test. You can also leverage code conversion patterns or OpenRewrite recipes. If you use other means of testing (such as Cucumber, camunda-bpm-scenario, and so on) you must adjust accordingly.
The Code Migration Detector (based on ArchUnit) can check how much Camunda 7 API is used in your codebase to allow you refactor to reduce the footprint step-by-step. Ideally, you can remove any Camunda 7 dependency at the end of your refactoring.
Improve Camunda 8 solution (optional)
One optional step many customers are doing is to adjust their solution to the latest Camunda best practices after migration. This allows you to reduce technical debt or remove workarounds that either crept into the solution over time or during the migration project for going live quickly. This step does not have to block the rollout of your migrated solution, and is often done after the fact to remove time pressure and incorporate any learnings from operating the Camunda 8 solution.
While this step can happen during code conversion already, it might also make sense to do it in a separate later step to reduce the number of changes during conversion to reduce the risk of breaking things.
While technically it is a great thing to improve your solution, many migration projects are under pressure to run efficiently (read: minimal effort). Therefore it is advisable to at least separate two different goals:
- Migrate the solution
- Improve the solution and reduce further technical debt
While Camunda sees a lot of value in doing both tasks at the same time - as you touch a lot of the code anyway and will probably also retest your solution thoroughly - if the budget is tight it might be better to focus on migration instead of not getting budgeted for the increased scope.
5Migrate data (optional)
With your solution code migrated, you also need to look at your production data. Camunda currently develops the Data Migrator to be used for this (planned to be available with 8.8). You might need to customize the data migrator, especially if you used complex data formats in C7 (for example, Java objects) that need to be converted to something Camunda 8 can handle (for example, JSON). As part of this step you might also need to extract big payloads and binaries (such as documents) into an external data store and reference it from the process (using for example upcoming document handling possibilities).
Data to be migrated includes runtime instances, audit data, and optimize data. Let's look at it one by one.
Runtime instances
Currently running process instances. Running means that these process instances in Camunda 7 are not yet ended and currently wait in some wait-state. This state is persisted in the database and a corresponding data entry needs to be created in Camunda 8, so that the process instance can continue from that state in the new solution.
Runtime instance migration has limitations, check migration tooling for details. As a result you might need to adjust your process models before migration. You can use process version migration in the Camunda 7 environment to migrate process instances to the version that is migratable to Camunda 8. An interesting strategy can be to define dedicated migration states you want your process instances to pile up in. Another common strategy is to use process instance modification in the Camunda 7 environment to move out of states that are not migratable (for example, process instances within a multiple instance task).
Migrating runtime instances is only necessary if you target a big bang migration for your process solution (keep in mind that "bing bang" in this context means to switch one process solution from Camunda 7 to Camunda 8 on a defined point in time - it doesn't mean that you have to migrate all your processes at once). If you drain out your Camunda 7 processes, or if they are typically very short-lived, you do not need runtime instance migration.
The Data Migrator needs to access the Camunda 7 database, but just uses Camunda 8 APIs, which means you can also use this tool when you run on SaaS.
Audit data (aka History)
Process instances left traces, often referred to as "history data". These are audit logs when a process instance was started, what path it took, and so on.
It is important to note, that audit data can exist for ended processes from the past, but is also available for currently still running process instances, as those process instances also left traces up to the current wait state.
If you need to preserve audit data and want to transfer it to Camunda 8, you can also use the Data Migrator. Migrating audit data comes with limitations (most prominently that you need to run Camunda 8 with RDBMS, a feature that is planned to be introduced with 8.9).
Migrating audit data is optional. If you need to do it, consider that audit data migration might need to look at a huge amount of data, which can take time to migrate. But you can run audit data migration beside the normal operations after a successful big bang migration over a period of time, which helps you to keep downtimes low.
Optimize data
The process intelligence tool Optimize keeps a lot of audit data to allow various analysis. This data might also want to be migrated when switching to Camunda 8.
Optimize data migration is currently not yet possible, but this is planned on the roadmap.
6Roll out
After you migrated the solution and prepared and tested the data migration (if necessary) you need to roll out your changes.
-
Drain out: In a drain out scenario you need to deploy your new solution next to the existing Camunda 7 solution. Then you need to add switching logic in your code, API gateway, or load balancer logic, which redirects traffic to your new solution. However, you still need to correlate callbacks to waiting process instances to the old solution, and might also present user tasks of both solutions to your users.
-
Big bang: In a big bang scenario, you will typically shutdown the old solution (or at least parts of it for the process under migration), then run the runtime instance migration to make sure all waiting process instances are transferred to the Camunda 8 solution. After this step succeeded, you can start up the new solution and route traffic to it. This approach assumes there can be a downtime of the application. If that is not an option, another alternative is to startup the C8 solution in parallel and just switch the traffic routing without downtime, and then start to migrate runtime instances afterwards.
Audit data migration can run after the switch has happened, after a successful drain-out (in parallel to normal operations) or of course during the downtime of a big bang. The best approach depends on the amount of data and the possibility for downtimes.
7Decommission Camunda 7 solution